| Project Name | Amount (Mil. Yen) | Interest Rate (% per annum) |
Repayment Period (years) | Grace Period (years) | Procurement |
|---|---|---|---|---|---|
| Ankara Water Supply Project | 26,826 | 1.5 | 25 | 7 | Untied |
DSI: General Directorate of State Hydraulic Works Address: Yucetepe 06100, ANKARA, TURKEY Tel/Fax: 90-312-425-8300
(1) Completion of the project: November 2013(with the completion of civil works)
(2) Issuing of letters of invitation for consulting services, including work monitoring: The executing agency will not employ the consultant for this project
(3) Tender announcement for procurement package for international competitive bidding on project construction:
Procurement package title: Regulator and Transmission Tunnel
Planned for: February 2010