1. Loan Amount and Terms

Project NameAmount (Mil. Yen)Interest Rate
(% per annum)
Repayment Period (years)Grace Period (years)Procurement
Ankara Water Supply Project26,8261.5257Untied

2. Executing Agency

DSI: General Directorate of State Hydraulic Works Address: Yucetepe 06100, ANKARA, TURKEY Tel/Fax: 90-312-425-8300

3. Planned implementation schedule

(1) Completion of the project: November 2013(with the completion of civil works)

(2) Issuing of letters of invitation for consulting services, including work monitoring: The executing agency will not employ the consultant for this project

(3) Tender announcement for procurement package for international competitive bidding on project construction:
Procurement package title: Regulator and Transmission Tunnel
Planned for: February 2010