Amount (mil.Yen) |
Amount (m.USD) |
Signing of E/N |
Project for Improvement of Equipment for Amelioration and Irrigation (Phase 2) |
777 |
7.45 |
April, 2013 |
Improvement of Emergency Medical Equipment in Baku City |
222 |
1.91 |
Mar. 2008 |
Improvement of Mushvig Substation in Baku |
880 |
7.93 |
May. 2006 |
Project for Improvement of Equipment for Amelioration and Irrigation |
624 |
5.11 |
Mar. 2004 |
Project for Improvement of Rehabilitative Equipment in Rehabilitation Centers |
412 |
3.38 |
Apr. 2002 |
Project for Trunk Route Rehabilitation |
372 |
3.54 |
Feb. 2001 |
Project for Improvement of Medical Equipment for Maternal and Child Hospitals |
507 |
4.30 |
Mar. 1999 |
Total |
3794 |
33.62 |
|
(2) Grand Aid for Increase of Food Production (2KR)/Grant Assistance for the Food Security Project for Underprivileged Farmers