Hydropower Plants Rehabilitation Project

Country, Site Myanmar
Project Outline The Project is to reduce the unplanned power outage and improve the remaining life of the power plants by rehabilitating the equipment of Baluchaung No.1 Hydropower Plant and Sedawgyi Hydropower Plant, thereby contributes to improvement in power supply of Myanmar.
Category B
Reason of
Categorization
The Project is not considered to have significant adverse impacts on the environment because it is not a large-scale power transmission and distribution line project as described in the JICA Guidelines for Environmental and Social Considerations (effective as of April 2010). Also, thieProject is not associated with sensitive characteristics or areas as described in the Guidelines.