  • The Japanese government extended the utilization of Project loan for Replenishment of materials used in Repair & Maintenance of NTDC's National Transmission lines affected by Flood 2022 in Pakistan.

Press Releases

January 16, 2023

The Japanese government extended the utilization of Project loan for Replenishment of materials used in Repair & Maintenance of NTDC's National Transmission lines affected by Flood 2022 in Pakistan.

Islamabd,16 Jan 2023: The Japanese government extended the project loan effective period upto 31 December 2024 of ongoing loan project "Punjab Transmission and Grid Stations Project (1). The loan agreement was signed on 3rd May 2008 under which Japan International Cooperation Agency (JICA) provided project-based loan of Japanese Yen 11,943,000,000/.

In this regard, the letter of amendment of loan agreement has been signed between JICA Headquarter, Tokyo, Japan and Ministry of Economic Affairs, Government of Pakistan. Additionally, JICA also accepted the utilization of remaining project loan amount for flood response.

The extension of loan utilization period will enable National Transmission and Dispatch Co Ltd (NTDC) to utilize remaining balance for the procurement of necessary materials as replenishment of essential materials in NTDC Warehouses which were urgency utilized for repair and maintenance of national transmission lines affected in the devastated flood 2022 across Pakistan.

The main objective of these projects were to improve the reliability and quality of power supply through the reduction of outages and voltage fluctuation and to meet the fast-growing load demand by strengthening transmission systems in Punjab province.

Through JICA support, NTDC has built one 500 kV Grid Station Rahim Yar Khan, 500/220 kV grid station at Faisalabad West along with associated transmission line, 220kV GIS grid station at Shalamar, Lahore along with associated transmission lines. The newly constructed 500/220 kV grid station at Faisalabad West along with associated transmission line will be expected to be operationalized soon.

Furthermore, the sub-stations and transmission lines constructed under JICA supported project contributed to mitigating the capacity ratio of neighboring substations and transmission system.