  • Signing of Japanese ODA Loan Agreements with Indonesia: Supporting the construction of a large-scale wastewater treatment plant for Jakarta and efforts for flood disaster prevention measures

Press Releases

【SDGs logo】CLEAN WATER AND SANITATION

【SDGs logo】INDUSTRY, INNOVATION AND INFRASTRUCTURE

【SDGs logo】SUSTAINABLE CITIES AND COMMUNITIES

April 1, 2020

Signing of Japanese ODA Loan Agreements with Indonesia: Supporting the construction of a large-scale wastewater treatment plant for Jakarta and efforts for flood disaster prevention measures

On March 31, the Japan International Cooperation Agency (JICA) signed loan agreements with the Government of the Republic of Indonesia in Jakarta, to provide Japanese ODA loans of up to a total of 64.36 billion yen for the following two projects.

(1) Jakarta Sewerage Development Project (Zone 1) (loan amount: 57.061 billion yen)
(2) Urban Flood Control System Improvement in Selected Cities (Phase 2) (loan amount: 7.299 billion yen)

Details for the projects are provided below.

(1) Jakarta Sewerage Development Project (Zone 1)

(a)Objective and Summary
This project involves constructing a large-scale wastewater treatment plant, along with a sewer network in Zone 1 of Jakarta, with the objectives of promoting proper wastewater treatment, improving the living environment and sanitation for residents, and conserving the aquatic environment. The project will contribute to the achievement of SDGs Goal 6.

(b) Executing Agency: Directorate General of Human Settlements, Ministry of Public Works and Housing
Address: Jl. Pattimura No. 20, Kebayoran Baru, Jakarta 12110, Republic of Indonesia.
TEL:+62-21-7397754、FAX:+62-21-7395226

(c) Planned Implementation Schedule
1. Completion of project: November 2025 – when the facilities are put into sevice.
2. Issuing of letters of invitation for supervising consulting services: April 2020.
3. Tender announcement of initial procurement package (Construction works) for international competitive bidding on project construction: Construction of WWTP, Construction of Sewers, expected release date: April 2020.

(2) Urban Flood Control System Improvement in Selected Cities (Phase 2)

(a)Objective and Summary
This project aims to improve the living environment and economic foundation of target areas that are highly prone to flood damage by supporting the construction of flood control infrastructure, enhancing the capacity of the river basin management offices and improving social consciousness.

This will support the reduction of risks related to floods in the target areas as well as enhance the capacity of flood risk management in the mid-term. The project will contribute to the achievement of SDGs Goals 9 and 11.

(b)Executing Agency: Directorate General of Water Resources, Ministry of Public Works and Housing
Address: SDA Building, 2nd Floor, Jl. Pattimura No. 20, Kebayoran Baru,
Jakarta 12110, Republic of Indonesia.
TEL/FAX:+62-21-739-6616

(c)Planned Implementation Schedule
1.Completion of project: November 2024 – when the facilities are put into service.
2.Issuing of letters of invitation for consulting services (including detailed design work): April 2020
3.Tender announcement of initial procurement package (Construction works) for international competitive bidding on project construction: No international competitive bidding is expected.

Terms and amounts of Loans

Project title Amount
(million yen)
Annual interest rate (%) Repayment
period
(years)
Grace
period
(years)
Procurement
Project Consulting services
Jakarta Sewerage Development Project (Zone 1) 57,061 1.2 0.01 25 7 General untied
Urban Flood Control System Improvement in Selected Cities (Phase 2) 7,299 0.80 0.01 20 6 General untied