Project News

2021-06-08

Strengthening Resilience on the Ground! - Construction Works at the Cyclone-Affected Facilities are in progress -

Renovation work of the public facilities damaged by the Cyclone Idai is being implemented at five sites in Beira city. The work has started in January 2021, but shortly thereafter Beira city has been hit by the Cyclone Eloise. Despite the severe situation caused by the cyclones and Covid-19, the construction works are progressing step by step. Under such a situation where people cannot travel freely, the project team members are controlling the work from Tokyo and Maputo by making the most of IT and digital technologies. One of them is the 360-degree-pictures that are stored in a cloud server. This system enables Japanese and Mozambican engineers to check the current and past site situation as if they were standing on the site.

PhotoThe 360-degree-pictures taken at the site are filed on a cloud server with the time record and shooting point. This enables the project team to grasp the situation easily.


The construction process and the recent pictures are shown below.

EPC Macurungo (Elementary School)

PhotoClassroom block H: Rehabilitation work
Roof removal work
23/02/2021

PhotoEmergency response work
Temporary classroom
21/04/2021


PhotoClassroom block A: New Construction
Situation of concrete casting
18/05/2021

PhotoClassroom block G: Rehabilitation work
Beam repair before roof work
20/05/2021


PhotoClassroom block B: New Construction
Bar arrangement of foundation beam and Pillar
20/05/2021

PhotoClassroom block A: New Construction
Situation after concrete casting
20/05/2021


ESG Mateus Sansão Muthemba (Secondary School)

PhotoBlock Q: Rehabilitation work
Roof removal work
10/02/2021

PhotoBlock Q: Rehabilitation work
Roof removal work is completed.
15/02/2021


PhotoBlock P: Rehabilitation work
Removal of damaged windows
08/03/2021

PhotoToilet Block V: Rehabilitation work
Demolition of existing walls is completed.
05/04/2021


PhotoToilet Block V: Rehabilitation work
Situation of masonry work
13/05/2021

PhotoBlock P: Rehabilitation work
New window frame installation
14/05/2021


PA Inhamizua e Sede de Bairro da Chingussura (Public office)

PhotoOffice Block S: Rehabilitation work
Windows removal
26/01/2021

PhotoOffice Block S: Rehabilitation work
Windows sample
28/02/2021


PhotoOffice Block S: Rehabilitation work
Roofing sheets removal, roof reinforcement work
05/04/2021

PhotoOffice Block S: Rehabilitation work
New window frame installation
19/05/2021


PhotoOffice Block S: Rehabilitation work
Roofing work is completed.
19/05/2021

PhotoExternal work: Rehabilitation work
Gravel pavement work
19/05/2021


ICS Beira (Training school for Health personal)

PhotoDormitory Block M:Emergency response work
Temporary roofing installation
23/02/2021

PhotoAcademic zone
Groundbreaking ceremony
05/03/2021


PhotoClassroom Block L: Rehabilitation work
Window repair
12/04/2021

PhotoClassroom Block E: New Construction
Bar arrangement and formwork for foundation
19/04/2021


PhotoClassroom Block L: Rehabilitation work
Reinforcement work for roof structure
12/04/2021

PhotoClassroom Block E: New Construction
Situation of foundation work
20/05/2021