2021-09-16

Progress of Construction Works at the Cyclone-Affected Facilities by remote supervision under COVID-19

Photo

Renovation and construction works of public facilities to ensure its resilience at five sites in Beira are on progress, which were damaged by the Cyclone Idai to hit the middle of Mozambique in March 2019. Seven months has passed since the work commenced. Due to the travel restriction from Japan under the COVID-19, remote construction supervision has continued and the project met a variety of problems at the project sites. However, local contractors and consultants have made every effort to solve the problems and the works move forward step by step. You can see the current situation of sites as below.

Please refer to the following web address for photos of the progress of construction work posted on this website in June 2021.


EPC Macurungo (Elementary School)

PhotoClassroom block G: Rehabilitation work
Installation of new wooden truss
27/08/2021

PhotoClassroom block G: Rehabilitation work
Installation of new purlins
30/08/2021


PhotoClassroom block A: New Construction
Concrete block laying for wall
03/08/2021

PhotoClassroom block A: New Construction
Re-bar setting for beams
27/08/2021


PhotoClassroom block A: New Construction
Re-bar setting and form work for beams
06/09/2021

PhotoSeptic tank: External work
Re-bar setting and form work for wall
06/09/2021


CFS Nhamatanda (Training center for Health personal)

PhotoRefectory block nE: Rehabilitation work
Situation of removal of existing roof
08/07/2021

PhotoRefectory block nE: Rehabilitation work
Eaves reinforcement by additional purlins
15/07/2021


PhotoRefectory block nE: Rehabilitation work
Eaves reinforcement by hurricane clips
15/07/2021

PhotoRefectory block nE: Rehabilitation work
Installation of new roof sheet
22/07/2021


PhotoRefectory block nE: Rehabilitation work
Installation of new ceiling furring
12/08/2021

PhotoRefectory block nE: Rehabilitation work
Installation of new ceiling board
02/09/2021


ESG Mateus Sansão Muthemba (Secondary School)

PhotoBlock P: Rehabilitation work
Window repair work
07/06/2021

PhotoBlock P: Rehabilitation work
Window repair work
28/08/2021


PhotoBlock P: Rehabilitation work
Rough installation of steel girder
30/08/2021

PhotoToilet Block V: Rehabilitation work
Situation of concrete casting
14/06/2021


PhotoToilet Block V: Rehabilitation work
Finishing work for interior wall
13/08/2021

PhotoToilet Block V: Rehabilitation work
Finishing work for water supply
06/09/2021


PA Inhamizua e Sede de Bairro da Chingussura (Public office)

PhotoOffice Block S: Rehabilitation work
Ceiling repair work
01/06/2021

PhotoOffice Block S: Rehabilitation work
Painting work on ceiling and wall
12/07/2021


PhotoOffice Block S: Rehabilitation work
Installation of new window
10/08/2021

PhotoOffice Block S: Rehabilitation work
Exterior painting work
27/08/2021


PhotoOffice Block S: Rehabilitation work
Repair work for parquet floor
06/09/2021

PhotoExternal work: Rehabilitation work
Situation of drinking fountain
03/09/2021


ICS Beira (Training school for Health personal)

PhotoClassroom Block E: New Construction
Concrete casting of slab
14/07/2021

PhotoClassroom Block E: New Construction
Concrete block laying for wall
24/07/2021


PhotoClassroom Block E: New Construction
Re-bar setting and form work for beams
02/09/2021

PhotoDormitory Block M: Rehabilitation work
Situation of roof reinforcement work
31/05/2021


PhotoRefectory Block N: Rehabilitation work
Eaves reinforcement with purlins
18/08/2021

PhotoClassroom Block L: Rehabilitation work
Window repair work
02/09/2021