Country, Site | Tanzania, Mtwara |
---|---|
Project Outline | The objective of the Project is to enhance the capacity of power supply through the construction of 300MW class Gas Turbine Combined Cycle (GTCC) Power Plant, 400kV Transmission line (T/L), Two (2) 400kV Substations (S/Ss), and associated 3-Infrastructures (road, gas pipeline and water pipeline). |
Category | A |
Reason of Categorization |
The project falls into the energy sector located in a sensitive area and is likely to have significant adverse impact due to its characteristic under the JICA guidelines for environmental and social considerations(April 2010). |
Latest Result of Monitoring |
- |
Past Results of Monitoring |
- |
Remarks | - |