Country, Site | Pakistan, Islamabad area |
---|---|
Project Outline | The objective of the Project is to enhance the reliability of the transmission system in/around the Islamabad area through the new construction of 220kV transmission line in/around the Islamabad area. |
Category | A |
Reason of Categorization |
The project falls into thetransmission lines sector located in a sensitive area and is likely to have significant adverse impact due to its characteristic under the JICA guidelines for environmental and social considerations (April 2010). |
Latest Result of Monitoring |
- |
Past Results of Monitoring |
- |
Remarks | - |
scroll