| Country, Site | Republic of Marshall Islands, Majuro Atoll |
|---|---|
| Project Outline | The objective of the Project is to increase the storage capacity of the reservoir in the Water Treatment Plant C by constructing a new reservoir, reparing exisiting reservoirs, and installing water inducing equipments. |
| Category | B |
| Reason of Categorization |
The project is not considered to be a large-scale water supply project, is not located in a sensitive area, and has none of the sensitive characteristics under the JICA guidelines for environmental and social considerations(April 2010), it is not likely to have a significant adverse impact on the environment. |
| Latest Result of Monitoring |
- |
| Past Results of Monitoring |
- |
| Remarks | - |