Country, Site | Olkaria Geothermal Area, Nakuru County, Kenya |
---|---|
Project Outline | The objective of the Project is to enhance volume and security of electric power supply in Kenya, by/through rehabilitating an existing geothermal power plant with power producing gross capacity from 45 MW to approximately 51 MW. |
Category | B |
Reason of Categorization |
The project is not located in a sensitive area, nor has sensitive characteristics, nor falls into sensitive sectors under the JICA Guidelines for Environmental and Social Considerations (April, 2010)., and its potential adverse impacts on the environment are not likely to be significant. |
Latest Result of Monitoring |
·Result of Monitoring (2024Q2) (PDF/1.4MB) |
Past Results of Monitoring |
- |
Remarks | - |